
| Citation | Hadley v Baxendale |
| Year of judgement | 23 february 1854 |
| court | Exchequer court |
| Case type | Contracts |
| Appellant | Hadley |
| Respondent | Baxendale |
| Bench | Parke B, Alderson B, Platt B and Martin B |
FACTS
The plaintiff carried on the business of millers and mealmen as co-partners and were owners and occupants of city steam mills in Gloucester. They went on with the only single-stream engine which is used for cleaning, grounding corn, and also for making it into flour, sharps and bran. They sustained on a single steam engine. The crankshaft of the mentioned steam engine was broken and in need of repair. This prohibited the steam engine from starting and even not functioning properly. The claimants wanted to have a new crankshaft made for the steam engine and then he contacted certain company members named W Joyce and co for the steam engine and they made a deal with them for a new steam engine. However, before a new shaft could be produced, the old shaft had to be sent to Greenwich so that the new shaft could be made to match the other parts of the steam engine. The defendants were hired by common carriers of goods and chattels from Gloucester to Greenwich Their business named Pickford and Sons they ran their business from Gloucester to Greenwich. Co. The plaintiffs gave the damaged shaft to the plaintiffs in exchange for compensation. The defendants agreed to deliver them on the second day after the contract. However, the defendant neglected and delivered the shaft delay of five days due to which the making of the new shaft took more time than usual, this affected the supply of flour to the plaintiff’s customers because the plaintiff’s mill closed for an additional five days. During that time there was a shortage of grains and profits due to the delay made by Baxendale (defendant). The plaintiff paid 2 pounds four shillings to ship the shaft and sued the defendant for 300 pounds in damages due to their loss.
ISSUES
Whether the defendant is liable for damages that were not aware of him at the time of the breach of the contract?
JUDGEMENT
The court determined that the standard rule for calculating damages in breach of contract cases is to award the claimant the amount they would have received if the breaching party had fulfilled their obligations. This means placing the plaintiff in the same position they would have been in if the breach had not occurred. However, in this specific case, the court decided that the damages should be those that naturally and reasonably arise from the breach itself or were reasonably foreseeable by both parties when they entered into the contract.
Furthermore, the court clarified that if there were unique circumstances known to both parties at the time of the contract, a breach would result in damages related to those circumstances. These damages would only be applicable if they were reasonably anticipated by both parties as a likely consequence of a breach. In this instance, the court ruled that Baxendale, the breaching party, was unaware of the mill shutdown and the extended closure, so the loss of profits couldn’t have been reasonably expected without Hadley, the claimant, communicating these special circumstances to Baxendale. Therefore, the court concluded that the jury should not have factored in the loss of profits when determining damages.
OBSERVATION
The test of remoteness is not satisfied
Therefore, if the consequence of the negligence act is foreseen by the ordinary man, then they are not too remote or if the ordinary man is unable to foresee the consequences, then they are too remote. the test solely depends on the thinking of the reasonable man.
The court’s ruling was based on the idea that a plaintiff can only be compensated for damages that were reasonably foreseeable when the contract was made or if there were specific circumstances both parties knew about when entering the contract, and the damages could be predicted based on those circumstances. The court also emphasized that if these special circumstances were not known to both parties, the defendant would only be responsible for damages that naturally result from a contract breach. This principle is meant to ensure fairness and prevent unfair advantage to either party. In this particular case, the special circumstance, which was not communicated to the defendants, was that the plaintiff had only one steam engine, and if it failed, their mill would stop. Therefore, the main reason for the decision was to ensure fairness and equality between the plaintiff and defendant, similar to the Hadley v. Baxendale case, and prevent unjust outcomes for the defendants.
REFERENCES
https://courtroomcast.lexisnexis.com
This Article is written by Saketi Neeharika of Damodaram Sanjivayya National Law University, Intern at Legal Vidhiya.

0 Comments