Site icon Legal Vidhiya

UNNAYAN BUILDERS PVT. LTD. VS SONA BERA,2018

Spread the love
CITATION2018 AIR 422, 2018 SCR (2) 702
DATE OF JUDGMENT16TH MARCH, 2018
COURTSUPREME COURT OF INDIA
APPELLANTUNNAYAN BUILDERS PVT. LTD.
RESPONDENTSONA BERA
BENCHV.K. JAIN JJ

INTRODUCTION

The instant appeal under Section 15 of the Consumer Protection Act, 1986 (hereinafter referred to as ‘the Act’) is at the behest of the Opposite Party to assail the Order No.17 dated 10.08.2016 passed by the Ld. District Consumer Disputes Redressal Forum, Kolkata, Unit-II (for short, Ld. District Forum) in Consumer Complaint No. 61/2016. By the impugned order, the Ld. District Forum allowed the complaint lodged by the Respondent under Section 12 of the Act with certain directions upon the Appellant/OP to refund amount of Rs.9,35,000/- along with interest thereon @ 9% p.a. w.e.f. 06.09.2010, to pay Rs.50,000/- compensation and penalty of Rs.50,000/- for unfair trade practice.

FACTS OF THE CASE

The Complainant Sona Bera W/o Arnab Bera entered into an agreement with the Opposite Party (OP) Unna yan Builders Private Limited (Petitioner) for purchasing a residential plot. The OP-Petitioner was required to provide the basic infrastructure while delivering possession of   the plot booked in a project namely ‘Unna yan Garden’ for a consideration ofRs.16,50,000/-. As per the terms of the agreement, the OP was to develop the plot within a period of   four years.  The OP having failed to carry out the requisite development by that date, the Complainant approached the concerned District Forum by way of a consumer complaint, seeking refund of the amount paid by him, along with compensation The complaint was resisted by the primarily on the ground that the Complainant had defaulted in payment of the balance instalments and therefore the complaint was liable to be dismissed. The District Forum having ruled in favour of the Complainant, the Petitioner (OP) approached the concerned State Commission by way of an appeal. The said appeal was also dismissed; the Petitioner (OP)filed a revision petition before the National Commission.

ISSUES RAISED

  1. Whether there was deficiency of service on part of the Opposite Party?

CONTENTIONS OF APPEALENT

CONTENTIONS OF REPONDENT

JUDGEMENT

The Petitioners contended that the agreement was not one of service but a contract of sale of a plot alone. Petitioners also argued that the agreement was liable to be set aside as the Complainant had not paid the balance instalment. The Commission observed that the non-payment of balance instalment was condoned by the Opposite Party and they had in fact not terminated the agreement. Thus, the agreement still stands.  The Commission opined that the Petitioners had to build some basic infrastructure before handing over the plot to the Complainant. Thus, there was an element of service presenting the agreement between the Complainant and the Opposite Party and they were deficient in providing the service. Based on the above discussion, the revision petition was dismissed. The Petitioners had to build some basic infrastructure before handing over the plot to the Complainant. Thus, there was an element of service present in the agreement between the Complainant and the Opposite Party and they were deficient in providing the service. Based on the above discussion the revision petition was dismissed.

Installing lifts without minimum power backup Petitioners had to build some basic infrastructure before handing over the plot to the Complainant. Thus, there was an element of service presenting the agreement between the Complainant and the Opposite Party and they were deficient in providing the service. Based on the above discussion, the revision petition was dismissed

ANALYSIS

  1. Legal Standards and Precedents – The analysis involved a careful examination of legal standards, including Section 15 of the Consumer Protection Act, 1986.
  2. Negligence and Accountability – The courts evaluated the evidence presented and determined that the appellant did not meet the expected standard of care. 
  3. Court’s Final Verdict – The case ultimately impugned order is modified to the extent that the appellant/OP refund the amount of Rs.9,35,000/- along with interest thereon @ 9% p.a. from the date of payment of respective instalments till the realisation of the same.

CONCLUSION

In conclusion, the impugned order is modified to the extent that the appellant/OP refund the amount of Rs.9,35,000/- along with interest thereon @ 9% p.a. from the date of payment of respective instalments till the realisation of the same. The order of payment of compensation of Rs.50,000/- imposed by the Ld. District Forum is maintained and the said amount must be paid within 30 days from date in default the amount shall carry interest @ 8% p.a. from date till its recover. With the above observations and directions, the appeal stands disposed of.

REFERENCES

  1. https://indiankanoon.org/
  2. https://www.scribd.com/

This Article is written by Shambhavi Singh student of Vivekananda Institute of Professional Studies, GGSIPU; Intern at Legal Vidhiya.

Disclaimer: The materials provided herein are intended solely for informational purposes. Accessing or using the site or the materials does not establish an attorney-client relationship. The information presented on this site is not to be construed as legal or professional advice, and it should not be relied upon for such purposes or used as a substitute for advice from a licensed attorney in your state. Additionally, the viewpoint presented by the author is of a personal nature.

Exit mobile version