Site icon Legal Vidhiya

Fateh Chand v/s Balkishan Das,1963 

Spread the love
CitationFateh Chand v/s Balkishan Das,1963 
Year of judgment 15 January 1923 
courtSupreme court 
Case type Contracts 
Appellant Fateh Chand 
Respondent Balkishan 
Bench Sinha, Bhuvaneshwar P.  (CJ), Gajendragadkar, P.B, Wanchoo, K.N., Gupta, K.C. Das, Shah, J.C  

FACTS

In a legal case from March 21, 1949, the plaintiff agreed to sell leasehold rights in land and a building to the defendant for Rs. 25,000. The plaintiff handed over possession, but the sale wasn’t completed within the stipulated time. They filed a suit to forfeit the Rs. 25,000 and gain possession and compensation. The defendant argued the plaintiff broke the contract and couldn’t forfeit the amount. The trial court ruled for the defendant to deposit Rs. 25,000 less Rs. 1,400 for possession. The High Court modified the decision, allowing the plaintiff to retain Rs. 11,250 and receive compensation for use. It was held that the defendant breached the contract. The court emphasized that penalties should be reasonable under the Indian Contract Act, Section 74. In this case, without proof of damage, the forfeiture of Rs. 1,000 and retention of Rs. 24,000 sufficed as compensation for the plaintiff. The High Court’s 10% compensation based on the contract price was not upheld, and the plaintiff was entitled to mesne profits and interest on them according to the Code of Civil Procedure, section 2(12). Rulings from Abdul Gani & Co. v. Trustees of the Port Bombay, I.L.R. 1952 Bom. 747 and Natesa Aiyar v. Appavu Padayachi, I.L.R. 38 Mad. 178 were distinguished.

ISSUES

  1. When does an Indian law interpret a liquidated damage clause as a penalty clause?
  2. What is the burden of proof for a party filing a claim under a Liquidated Damage Clause?
  3. Is it necessary to prove real loss, as in a claim under Section 73 of the Indian Contract Act, or is the evidence threshold different?

JUDGMENT 

The Court stated that the Case concerning a breach of contract and the subsequent legal implications. The discussion primarily centers on the interpretation and application of Section 74 of the Indian Contract Act, which deals with the concept of stipulated compensation in the event of a contract breach. The section highlights two critical conditions regarding compensation for breach of contract. The first condition emphasizes the amount “to be paid in case of such breach,” while the second condition mentions “any other stipulation by way of penalty” present in the contract. The courts seem to have predominantly focused on the first condition, overlooking the broader implication of the second condition relating to penalties.

The section establishes the legal framework for determining liability in breach of contract cases, be it through predetermined compensation or stipulations of penalties. It ensures that despite predetermined damages or penalties outlined in the contract, the court will grant only reasonable compensation to the aggrieved party, not exceeding the specified amount or penalty. Crucially, this application of the law is not limited to cases where the aggrieved party acts as a plaintiff. The court’s jurisdiction is not determined by the plaintiff or defendant status. Instead, it is about ascertaining fair compensation for the aggrieved party, considering the conditions at the time of the breach. The purpose is to compensate the party for losses incurred due to the breach, and this compensation should be reasonable and commensurate with the situation. In this case, the breach of contract did not demonstrate specific losses suffered by the plaintiff. The contract had stipulated a forfeiture of a certain amount in case of breach. However, the court deemed a 10 percent penalty on the agreed price as unreasonable without evidence of actual damages. The court recognized the forfeiture of the earnest money as appropriate but found no grounds for awarding compensation amounting to 10 percent of the contract price.

The case also delves into the computation of mesne profits, emphasizing that such profits should be based on the value of the use of the property. The court dismissed an artificial approach of basing compensation on an estimated return related to the property value. the court interpreted the application of Section 74 of the Indian Contract Act, particularly in the context of stipulated compensation and penalties for breach of contract. The court’s deliberations highlight the importance of reasonable compensation based on actual losses incurred due to the breach, promoting fairness and equity in contract law.

Observation 

According to the Court’s decision, a penalty term in a contract applies widely, covering numerous stipulations concerning penalties, whether in the form of monetary payment or other sorts of penalties such as forfeiture. If liquidated damages (LD) clauses mimic penalties, the court may award appropriate compensation up to the specified sum without needing proof of actual loss or harm. However, a legal injury must still be proven before compensation can be granted under Section 74 of the Contract Act. Essentially, parties can profit from an LD provision without the same level of proof required in a Section 73 case, especially if the contract expressly states the damages as a pre-estimate agreed upon by both parties and not meant as a penalty.

REFERENCE

https://lawdocs.in

https://www.barandbench.com

This Article is written by Saketi Neeharika of Damodaram Sanjivayya National Law University, Intern at Legal Vidhiya.

Exit mobile version