Site icon Legal Vidhiya

HALLIBURTON OFFSHORE SERVICES v VEDANTA LTD. & ANR.

Spread the love
O.M.P (I) (COMM) &I.A.3697/2020
ORDER DATEDApril 20, 2020
COURT High Court of Delhi
PETITIONERM/s Halliburton Offshore Services Inc.
RESPONDENT Vedanta Limited and Another
CORAMHon’ble Mr. Justice C. Hari Shankar

INTRODUCTION-

‘M/s Halliburton Offshore Services Inc. vs Vedanta Limited and Another’ is a recent case displaying the complexities of bulky contracts and their interpretation according to the disputes that arose. 

In this case, the question is regarding the imposition of lockdown and the consequences thereof. The central idea about this is whether any of the delay which is majorly because of the lockdown is maintainable or not.

The respondents here wanted to terminate the contract and get their guarantees encashed due to the incomplete work on part of petitioners, this case analyzes whether this is the right way or not.

All the material points about this are discussed herein under.

FACTS OF THE CASE-

ISSUES RAISED-

  1. Whether the present situation falls under Force Majeure clause.
  2. Whether the petitioner can get the restraining order. 

CONTENTIONS OF THE PETITIONER-

  1. That they had been granted extension for completion of project till 31st March 2020 and a substantial portion of work was completed prior this date and because of the lockdown in industrial activities and restrictions on the movement of people due to COVID-19 the petitioner was unable to perform the contract.
  2. As for the completion of the project, there was a requirement of workmen to travel overseas and that was impossible owing to lockdown.

CONTENTIONS OF THE RESPONDENT-

  1. The petitioner had to complete the work of 3 wells by 16th January 2019, 16th March 2019, 16th June 2019 respectively. Even after this, the respondent agreed to extend time till 31st March 2020 to complete the project.
  2. That the petitioner had raised the issue of force majeure for the first time on March 2020 and that too just for reaping benefits and hiding their own faults.
  3. That the work which was assigned to the petitioner stood excepted from the lockdown as imposed by the Government.

JUDGEMENT-

The fact that the countrywide lockdown which was imposed from 24th March 2020 is unprecedented and a pandemic of nature which affects the complete world and which none of us had experienced in our life and hopefully would never either. 

As the respondent mentioned that the kind of work which the petitioner was assigned was exempted from the lockdown or so. Now, even if petroleum stood as an essential commodity, the petitioner was not producing it in a strict sense, rather they were drilling wells, which if not completely but substantially was hindered and impeded due to lockdown.

The court being aware of all facts and circumstances, in view of pandemic and situation of lockdown, grants an ad interim injunction to restrain invocation or encashment of the said eight Guarantees, till the expiry of one week from 3rd May 2020, till which date the lockdown shortly stands extended.

As to this injunction’s merits would be heard on next hearing consequent to pleadings and all formal requirements completion.

ANALYSIS-

  1. Force Majeure– Those circumstances which are unforeseeable and which prevents a party from fulfilling their part of contract. It is a French term which literally means ‘greater force’ and is related to the Act of God. For such acts no party can be held liable. 
  1. Ad interim injunction-the kind of legal remedy which aims to maintain status quo in the existing situation and allows the party to seek prompt relief and prevent any infringement. 
  1. Encashing Guarantee- Bank guarantee is something which implies that a bank will cover an eventuality. In case that eventuality occurs, may be in default of payment, the party holding the guarantee can ask the guarantor to pay that amount which when done by bank is said to be encashed.

CONCLUSION-

This case is crucial from the view that it highlights the COVID situation and its vulnerabilities. This case itself is a precedent for it allows lockdown as an excuse for the delay of performance of contract on part of petitioner.

The Court in this case gave an interim order of injunction restraining the respondent to maintain status quo and to keep guarantees in the same situation till next hearing. 

This case highlights that certain situations are not under our control and the recourse for that should also be changed in such cases. This points out the development which our justice system or the country is doing as of now. We are not accustomed to static point of views in unexpectedly changed circumstances and are ready to welcome the status required as of now.

REFERENCES-

  1. indiankanoon.org
  2. images.assettype.com

This Article is written by Devanshi Goyal, student of Faculty of law, JNVU, Jodhpur; Intern at Legal Vidhiya.

Disclaimer: The materials provided herein are intended solely for informational purposes. Accessing or using the site or the materials does not establish an attorney-client relationship. The information presented on this site is not to be construed as legal or professional advice, and it should not be relied upon for such purposes or used as a substitute for advice from a licensed attorney in your state. Additionally, the viewpoint presented by the author is of a personal nature.

Exit mobile version